No.02/2009 DREDGING WORKS IN CARDIFF BAY BARRAGE OUTER HARBOUR AND APPROACH CHANNEL
Harbourmaster
Tel: (029) 2087 7900
Barrage control
Tel: (029) 2070 0234
VHF
vhf channel 18
Beginning on or around Monday 26th January 2009, the vessel ‘Alec D’ will reposition the four channel marker buoys located in the approach channel to Cardiff Barrage Outer Harbour outside of the channel prior to the commencement of dredging operations. This will be complete by Saturday 31st January 2009.
Beginning on or around Sunday 1st February 2009, for approximately 3 weeks, the vessels MV Sospan and Avanti ‘C’ will be carrying out dredging works in Cardiff Bay Barrage Outer Harbour and approach channel.
The vessels will display lights and shapes in accordance with the International Regulations for the Prevention of Collisions at Sea and will maintain a listening watch on VHF Channel 16, 69 & 18.
Vessels wishing to enter or leave Cardiff Bay should contact Barrage Control on VHF Channel 18 and await instructions before entering the Outer Harbour.
----------------------------------------------------------------------------------
No.01/2009 LIGHTING INSTALLATION WORKS – WOOD STREET RAILWAY BRIDGE ON THE RIVER TAFF
Harbourmaster
Tel: (029) 2087 7900
Barrage control
Tel: (029) 2070 0234
VHF
vhf channel 18
From Monday 26th January 2009, for approximately two weeks, lighting installation works will take place on the upstream end of the arches on Wood Street railway bridge on the River Taff.
Works will take place between 0800 hrs and 1630 hrs, Monday to Friday and will be undertaken from a pontoon structure.
A work/safety boat will be in attendance at all times when installation work is being undertaken.
Mariners are requested to navigate with caution in this area and at dead slow speed.
Harbourmaster
Tel: (029) 2087 7900
Barrage control
Tel: (029) 2070 0234
VHF
vhf channel 18
Beginning on or around Monday 26th January 2009, the vessel ‘Alec D’ will reposition the four channel marker buoys located in the approach channel to Cardiff Barrage Outer Harbour outside of the channel prior to the commencement of dredging operations. This will be complete by Saturday 31st January 2009.
Beginning on or around Sunday 1st February 2009, for approximately 3 weeks, the vessels MV Sospan and Avanti ‘C’ will be carrying out dredging works in Cardiff Bay Barrage Outer Harbour and approach channel.
The vessels will display lights and shapes in accordance with the International Regulations for the Prevention of Collisions at Sea and will maintain a listening watch on VHF Channel 16, 69 & 18.
Vessels wishing to enter or leave Cardiff Bay should contact Barrage Control on VHF Channel 18 and await instructions before entering the Outer Harbour.
----------------------------------------------------------------------------------
No.01/2009 LIGHTING INSTALLATION WORKS – WOOD STREET RAILWAY BRIDGE ON THE RIVER TAFF
Harbourmaster
Tel: (029) 2087 7900
Barrage control
Tel: (029) 2070 0234
VHF
vhf channel 18
From Monday 26th January 2009, for approximately two weeks, lighting installation works will take place on the upstream end of the arches on Wood Street railway bridge on the River Taff.
Works will take place between 0800 hrs and 1630 hrs, Monday to Friday and will be undertaken from a pontoon structure.
A work/safety boat will be in attendance at all times when installation work is being undertaken.
Mariners are requested to navigate with caution in this area and at dead slow speed.